Danube Properties Danube Properties 8005757 info@danubeproperties.ae

Gemz

CONSTRUCTION UPDATES

Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
CHECK MORE UPDATES
2024-03-31

1 All regularities are obtained.

2 Mobilization is completed.

3 Shoring is completed.

4 Piling is completed.

5 Excavation is completed.

6 Substructure is completed.

7 Superstructure is completed.

8 Block and Plaster works completed upto roof floor.

9 Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.

10 Chillers received and installed at roof.

11 Façade work is in progress and on schedule.

12 Elevator installation works in progress.

13 All Long Lead Items are delivered.

14 Project development in progress.

15 Project scheduled to be finished on time.

2024-03-15

- All regularities are obtained.

- Mobilization is completed.

- Shoring is completed.

- Piling is completed.

- Excavation is completed.

- Substructure is completed.

- Superstructure is completed.

- Block and Plaster works completed upto 15th floor.

- Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.

- Chillers received and installed at roof.

- Façade work is in progress and on schedule.

- Elevator installation works in progress.

- All Long Lead Items are delivered.

- Authority approvals are in progress.

- Project development in progress.

- Project scheduled to be finished on time.

PROGRESS ( 31-Mar-2024 )

Excavation
100%
Shoring
100%
Concrete
93.24%
Blockwork
72.27%
Internal Plaster
60.97%
Electrical
21.23%
Hvac
35%
Glass Aluminium
3.85%
Wooden doors
0.94%
Wardrobe
1.11%
Kitchen
1.11%
Plumbing
36.74%
External Plaster
10%
Internal Paint
7.5%
External Paint
0%
Tiling Marble
16.56%
Mechanical
36.74%
Handrail Fencing
2.5%
False ceiling
4.6%
Lighting
0%
Bath sanitary
0%