Danube Properties Danube Properties 8005757 info@danubeproperties.ae

Olivz By Danube

CONSTRUCTION UPDATES

Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
CHECK MORE UPDATES
2024-03-31

1 Building completion certificate obtained.

2 Testing & Commissioning completed.

3 Project at handing over stage.

2024-03-15

1 Building completion certificate obtained.

2 Testing & Commissioning completed.

3 Project at handing over stage.

PROGRESS ( 31-Mar-2024 )

Excavation
100%
Shoring
100%
Concrete
100%
Blockwork
100%
Internal Plaster
100%
Electrical
95%
Hvac
0%
Glass Aluminium
99%
Wooden doors
95%
Wardrobe
96%
Kitchen
96%
Plumbing
0%
External Plaster
100%
Internal Paint
88%
External Paint
88%
Tiling Marble
98%
Mechanical
95%
Handrail Fencing
98%
False ceiling
97%
Lighting
83%
Bath sanitary
83%