2024-03-31

Viewz 2.

1 Guide Wall completed.

2 Shoring works completed.

3 Excavation works of Enabling contractor is completed.

4 Enabling contractor handed over the site to Main Contractor.

5 Main pile design submitted and approved by DM.

6 Piling works started. And in progress

7 Capping beam completed.

8 Dewatering system submitted for authority approval.

9 All Engineering submissions are in progress.

10 Main contractor on board.

11 Project is scheduled to be completed on time.

" >

Viewz 1.

1 All regularities are obtained.

2 Moblization is completed.

3 Shoring is completed.

4 Piling is completed.

5 Excavation is completed.

6 Substructure is completed.

7 Superstructure - 13th floor in progress. 14th floor

8 Block works completed upto 6th floor. 7 & 8 on progress

9 Plaster works completed upto 2nd fllor. 3rd floor in progress.

10 Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work. 11 Project development in progress.

Viewz 2.

1 Guide Wall completed.

2 Shoring works completed.

3 Excavation works of Enabling contractor is completed.

4 Enabling contractor handed over the site to Main Contractor.

5 Main pile design submitted and approved by DM.

6 Piling works started. And in progress

7 Capping beam completed.

8 Dewatering system submitted for authority approval.

9 All Engineering submissions are in progress.

10 Main contractor on board.

11 Project is scheduled to be completed on time.

" >

Viewz 1.

1 All regularities are obtained.

2 Moblization is completed.

3 Shoring is completed.

4 Piling is completed.

5 Excavation is completed.

6 Substructure is completed.

7 Superstructure - 13th floor in progress. 14th floor

8 Block works completed upto 6th floor. 7 & 8 on progress

9 Plaster works completed upto 2nd fllor. 3rd floor in progress.

10 Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work. 11 Project development in progress.

Viewz 2.

1 Guide Wall completed.

2 Shoring works completed.

3 Excavation works of Enabling contractor is completed.

4 Enabling contractor handed over the site to Main Contractor.

5 Main pile design submitted and approved by DM.

6 Piling works started. And in progress

7 Capping beam completed.

8 Dewatering system submitted for authority approval.

9 All Engineering submissions are in progress.

10 Main contractor on board.

11 Project is scheduled to be completed on time.

" >

Viewz 1.

1 All regularities are obtained.

2 Moblization is completed.

3 Shoring is completed.

4 Piling is completed.

5 Excavation is completed.

6 Substructure is completed.

7 Superstructure - 13th floor in progress. 14th floor

8 Block works completed upto 6th floor. 7 & 8 on progress

9 Plaster works completed upto 2nd fllor. 3rd floor in progress.

10 Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work. 11 Project development in progress.

Viewz 2.

1 Guide Wall completed.

2 Shoring works completed.

3 Excavation works of Enabling contractor is completed.

4 Enabling contractor handed over the site to Main Contractor.

5 Main pile design submitted and approved by DM.

6 Piling works started. And in progress

7 Capping beam completed.

8 Dewatering system submitted for authority approval.

9 All Engineering submissions are in progress.

10 Main contractor on board.

11 Project is scheduled to be completed on time.

2024-03-15

1 Fencing work completed.

2 Shoring Guide wall casting completed.

3 Shoring Piles casting is in progress.

4 Soil shifting is in progress.

5 Capping Beam casting is in progress.

6 Dewatering system submitted for authority approval.

7 All Engineering submissions are in progress.

8 Piling design approved.

9 Main contractor on board.

10 Project is scheduled to be completed on time.