1 Mobilization is completed.
2 All regularities are obtained.
3 Shoring is completed.
4 Piling is completed.
5 Excavation is completed.
6 Substructure is completed.
7 Superstructure - 14th Floor in progress.
8 Block works completed upto 10th floor.
9 Plaster works completed upto 5th floor.
10 Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.
1 Mobilization is completed.
2 All regularities are obtained.
3 Shoring is completed.
4 Piling is completed.
5 Excavation is completed.
6 Substructure is completed.
7 Superstructure - 13th Floor in progress.
8 Block works completed upto 9th floor.
9 Plaster works completed upto 4th floor.
10 Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.