2024-03-31

1 Project completed.

2 Building completion certificate obtained.

3 Testing & Commissioning in progress.

4 Project at handing over stage.

2024-03-15

1 Project completed.

2 Building completion certificate obtained.

3 Testing & Commissioning in progress.

4 Desnagging in progress.

PROGRESS ( 31-Mar-2024 )

Excavation
100%
Shoring
100%
Concrete
100%
Blockwork
100%
Internal Plaster
100%
Electrical
90%
Hvac
90%
Glass Aluminium
96%
Wooden doors
95%
Wardrobe
90%
Kitchen
92%
Plumbing
90%
External Plaster
100%
Internal Paint
75%
External Paint
90%
Tiling Marble
95%
Mechanical
90%
Handrail Fencing
98%
False ceiling
96%
Lighting
85%
Bath sanitary
85%