1 All regularities are obtained.
2 Moblization is completed.
3 Shoring is completed.
4 Piling is completed.
5 Excavation is completed.
6 Substructure is completed.
7 Superstructure - 13th floor in progress. 14th floor
8 Block works completed upto 6th floor. 7 & 8 on progress
9 Plaster works completed upto 2nd fllor. 3rd floor in progress.
10 Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.
11 Project development in progress.
1 All regularities are obtained.
2 Moblization is completed.
3 Shoring is completed.
4 Piling is completed.
5 Excavation is completed.
6 Substructure is completed.
7 Superstructure - 13th floor in progress.
8 Block works completed upto 6th floor.
9 Plaster works completed upto 2nd fllor.
10 Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.
11 Authority approvals are in progress.
12 Project development in progress.